Mep Work Progress Report Sample

If you want this tailored to a different project type, format (weekly/fortnightly), or as an editable Word/Excel template, tell me which and I’ll produce it.

[Name / Title] Date: ___________________ mep work progress report sample

Revised BIM model shared; sprinkler heads relocated as per updated shop drawings. 5. PLANNED WORK FOR NEXT PERIOD Commence cable pulling for the LV main panels. If you want this tailored to a different

systems are the "heart and lungs" of any building. Because these systems are complex and highly interdependent, a clear MEP work progress report PLANNED WORK FOR NEXT PERIOD Commence cable pulling

Use S-Curves and Gauges to show planned vs. actual progress. Be Accurate:

| Trade | Actual (Daily Avg) | Planned | Variance | Equipment Used | | :--- | :--- | :--- | :--- | :--- | | | 12 | 14 | -2 (Sick leave) | Scissor Lifts (2), Pipe Threader | | Electrical | 18 | 16 | +2 (Overtime) | Cable pullers, Benders | | Plumbing | 8 | 8 | 0 | Welders (2) | | Helpers/Labors | 10 | 10 | 0 | - |